DESIGN, SUPPLY AND INSTALLATION OF 30KW HYBRID SOLAR PV SYSTEM FOR BASIRMA PHCC in Erbil, IRAQ.

UNHCR
DESIGN, SUPPLY AND INSTALLATION OF 30KW HYBRID SOLAR PV SYSTEM FOR BASIRMA PHCC in Erbil, IRAQ. Request for proposal

Reference: HCR/IRQER/2020/RFP-039
Beneficiary countries or territories: Iraq
Published on: 23-Nov-2020
Deadline on: 23-Dec-2020 23:59 (GMT 3.00)

Description

Design, Supply and Installation of 30 KW Hybrid solar PV system for Basirma PHCC -IRAQ

  • The project of Design, Supply, and Installation of 30 KW Hybrid solar PV system for Basirma PHCC is to provide the PHCC with backup power supply during the working time and cover the shortage of electricity.
  • The selected company will be responsible for designing a PV solar system (30 KW) with all details and submit it to the UNHCR technical unit for approval before starting the work.
  • Before starting the work, the contractor is responsible for submitting all certificate of origin.
  • The work includes fixing an aluminium structure fit for 78 PV panels at the roof of the PHCC and installing three hybrid inverters (10 kW each) inside the PHCC connected with the mainboard outside.
  • Also re-arrange all wiring inside the PHCC to make sure that we have two feeder lines: one for the critical load connected with the PV solar system and the other for the normal load.
  • The aluminium structure, PV panels and inverter must be earthed.
  • All PV cables at the roof or standard cables outside the PHCC must be covered by cable tray, PVC pipes or flex pipe.
  • UNHCR engineers and or third-party will inspect the quality of the work implemented by the contractor. The work must be within engineering specifications/standards and time limit.

------------------------------------------------------------------------------------------------

Site visit : 06 December 2020 at 10:30 AM Local time

Last day for Queries : 08 December 2020, 17:00 hrs. Iraq Local Time

Closing date for submission of bids : 23 December 2020, 23:59 hrs. Iraq Local Time.

Venue: Basirma Sub-town, Erbil..

---------------------------------------------------

All Bidders are kindly advised that Addendum no. 1, Revised Annex C, Revised Annex A, Roof Drawing, Required Electrical Power & Q&A document have been uploaded here.